{"id":21506,"date":"2025-05-19T00:09:18","date_gmt":"2025-05-18T15:09:18","guid":{"rendered":"https:\/\/xlworks.net\/?p=21506"},"modified":"2025-05-19T00:09:18","modified_gmt":"2025-05-18T15:09:18","slug":"xlgantt-howto-14-workloads","status":"publish","type":"post","link":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/","title":{"rendered":"Excel Gantt Chart - How to #14 \u2013 Workload calculation"},"content":{"rendered":"<p>Let's take a look at how to calculate the workload when scheduling a project.<\/p>\n<p>As shown below, if the start date of the \u201cDesign database\u201d task is July 22 and the finish date is July 31, the working days(excluding nonworking days) are 8.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21507\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_04-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?fit=525%2C225&amp;ssl=1\" data-orig-size=\"525,225\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_04\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?fit=300%2C129&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?fit=525%2C225&amp;ssl=1\" class=\"alignnone wp-image-21507 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?resize=525%2C225&#038;ssl=1\" alt=\"Workload calculation\" width=\"525\" height=\"225\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?w=525&amp;ssl=1 525w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?resize=300%2C129&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?resize=150%2C64&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04.png?resize=210%2C90&amp;ssl=1 210w\" sizes=\"auto, (max-width: 525px) 100vw, 525px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21509\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_01-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?fit=308%2C343&amp;ssl=1\" data-orig-size=\"308,343\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_01\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?fit=269%2C300&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?fit=308%2C343&amp;ssl=1\" class=\"alignnone wp-image-21509 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?resize=308%2C343&#038;ssl=1\" alt=\"Workload calculation\" width=\"308\" height=\"343\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?w=308&amp;ssl=1 308w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?resize=269%2C300&amp;ssl=1 269w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?resize=135%2C150&amp;ssl=1 135w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_01.png?resize=126%2C140&amp;ssl=1 126w\" sizes=\"auto, (max-width: 308px) 100vw, 308px\" \/><\/p>\n<p><span style=\"color: #993300;\">\u203b Refer to the following link for setting nonworking days and calculating the workload.<\/span><\/p>\n<p><a href=\"https:\/\/xlworks.net\/en\/?p=21456\" target=\"_blank\" rel=\"noopener noreferrer\">Excel Gantt Chart - How to #11 \u2013 Calendar<\/a><\/p>\n<p>&nbsp;<\/p>\n<p>If only one person is assigned half a day or several people are assigned to the \u201cDesign database\u201d task, the workload should be calculated as follows.<\/p>\n<ul>\n<li>If only 50% (only half a day) is allocated, the workload should be calculated as 8 days * 50% = 4 days.<\/li>\n<li>If 2 people are assigned, the workload should be calculated as 8 days * 2 people = 16 days.<\/li>\n<\/ul>\n<p>For the above case, XLGantt provides the following two methods of calculating the workload.<\/p>\n<ul>\n<li>Calculated by resource allocation ratio (provided from version 4.0)<\/li>\n<li>Calculated by weight<\/li>\n<\/ul>\n<p>In the ribbon menu \u201cXLGantt&gt; Options&gt; General&gt; Workload Calculation\u201d, you can select the workload calculation method.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21511\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_02-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?fit=557%2C575&amp;ssl=1\" data-orig-size=\"557,575\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_02\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?fit=291%2C300&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?fit=557%2C575&amp;ssl=1\" class=\"alignnone wp-image-21511 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?resize=557%2C575&#038;ssl=1\" alt=\"Workload Calculation option\" width=\"557\" height=\"575\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?w=557&amp;ssl=1 557w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?resize=291%2C300&amp;ssl=1 291w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?resize=145%2C150&amp;ssl=1 145w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_02.png?resize=136%2C140&amp;ssl=1 136w\" sizes=\"auto, (max-width: 557px) 100vw, 557px\" \/><\/p>\n<p>&nbsp;<\/p>\n<h2>1. Calculated by resource allocation ratio<\/h2>\n<p>\"Calculated by resource allocation ratio\" is a feature added from version 4.0.<\/p>\n<p>If you enter \u201cElsa, Mike\u201d or \u201cElas[50%], Mike\" in the \"Resources\" column\u00a0of the Schedule sheet, the workload is calculated according to the percentage of the assigned personnel.<br \/>\nYou can check the workload assigned to each person in the \"Progresses by Resources\" and \"Workloads\" features(You can use the feature from the ribbon menu XLGantt tab&gt; Analysis group).<\/p>\n<h3>1) When one person is assigned to one task<\/h3>\n<p>If nothing is entered in the \"Resources\" column\u00a0or if only one name of the assigned personnel is entered, it is assumed that one person is assigned.<\/p>\n<p>If nothing is entered in the \"Resources\" column, it is assumed that one person is assigned and the total workload is calculated as 8 days.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21513\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_05-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?fit=525%2C225&amp;ssl=1\" data-orig-size=\"525,225\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_05\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?fit=300%2C129&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?fit=525%2C225&amp;ssl=1\" class=\"alignnone wp-image-21513 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?resize=525%2C225&#038;ssl=1\" alt=\"When one person is assigned to one task\" width=\"525\" height=\"225\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?w=525&amp;ssl=1 525w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?resize=300%2C129&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?resize=150%2C64&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_05.png?resize=210%2C90&amp;ssl=1 210w\" sizes=\"auto, (max-width: 525px) 100vw, 525px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p>if only one name of the assigned personnel is entered in the resources column, it is assumed that one person is assigned and the total workload is calculated as 8 days.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21515\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_04-3\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?fit=525%2C225&amp;ssl=1\" data-orig-size=\"525,225\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_04\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?fit=300%2C129&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?fit=525%2C225&amp;ssl=1\" class=\"alignnone wp-image-21515 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?resize=525%2C225&#038;ssl=1\" alt=\"When one person is assigned to one task\" width=\"525\" height=\"225\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?w=525&amp;ssl=1 525w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?resize=300%2C129&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?resize=150%2C64&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_04-1.png?resize=210%2C90&amp;ssl=1 210w\" sizes=\"auto, (max-width: 525px) 100vw, 525px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p>\u203b The \u201cplanned work\u201d displayed on the right side of the \"total work\" is the workload to be carried out until today. The basic calculation method is the same as the \"total work\", except that it is calculated by the working days until today.<\/p>\n<p>&nbsp;<\/p>\n<h3>2) When a part of the resource is allocated to one task<\/h3>\n<p>If you enter \u201cElsa [50%]\u201d in the \"Resources\" column, only half will be calculated.<\/p>\n<p><span style=\"color: #993300;\">Total workload = number of working days excluding nonworking days\u00a0 * Number of entered people (Elsa [50%])<\/span><br \/>\n<span style=\"color: #993300;\">4 days = 8 days * 50% (0.5 Elsa)<\/span><\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21517\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_06-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?fit=522%2C224&amp;ssl=1\" data-orig-size=\"522,224\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_06\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?fit=300%2C129&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?fit=522%2C224&amp;ssl=1\" class=\"alignnone wp-image-21517 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?resize=522%2C224&#038;ssl=1\" alt=\"When a part of the resource is allocated to one task\" width=\"522\" height=\"224\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?w=522&amp;ssl=1 522w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?resize=300%2C129&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?resize=150%2C64&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_06.png?resize=210%2C90&amp;ssl=1 210w\" sizes=\"auto, (max-width: 522px) 100vw, 522px\" \/><\/p>\n<p>&nbsp;<\/p>\n<h3>3) When multiple people are assigned to a single task<\/h3>\n<p>If you enter multiple names in the resources column, the workload is calculated as follows.<\/p>\n<p><span style=\"color: #993300;\">Total workload = number of working days excluding nonworking days * Number of people entered (Elsa, Mike)<\/span><br \/>\n<span style=\"color: #993300;\">16 days = 8 days * 2 people<\/span><\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21519\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_07-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?fit=521%2C225&amp;ssl=1\" data-orig-size=\"521,225\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_07\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?fit=300%2C130&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?fit=521%2C225&amp;ssl=1\" class=\"alignnone wp-image-21519 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?resize=521%2C225&#038;ssl=1\" alt=\"When multiple people are assigned to a single task\" width=\"521\" height=\"225\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?w=521&amp;ssl=1 521w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?resize=300%2C130&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?resize=150%2C65&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_07.png?resize=210%2C91&amp;ssl=1 210w\" sizes=\"auto, (max-width: 521px) 100vw, 521px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p>The result is the same as above even if you enter \"Elsa[100%], Mike[100%]\" as follows.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21521\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_08-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?fit=584%2C223&amp;ssl=1\" data-orig-size=\"584,223\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_08\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?fit=300%2C115&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?fit=584%2C223&amp;ssl=1\" class=\"alignnone wp-image-21521 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?resize=584%2C223&#038;ssl=1\" alt=\"When multiple people are assigned to a single task\" width=\"584\" height=\"223\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?w=584&amp;ssl=1 584w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?resize=300%2C115&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?resize=150%2C57&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_08.png?resize=210%2C80&amp;ssl=1 210w\" sizes=\"auto, (max-width: 584px) 100vw, 584px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p>It can be calculated even if several people are assigned as follows or only a part of a specific person is assigned.<\/p>\n<p><span style=\"color: #993300;\">Total workload = Number of working days excluding nonworking days * Number of people entered (Elsa[50%], Mike)<\/span><br \/>\n<span style=\"color: #993300;\">12 days = (8 days * 50% (0.5 Elsa)) + (8 days * 1 Mike)<\/span><\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21523\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_09-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?fit=583%2C223&amp;ssl=1\" data-orig-size=\"583,223\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_09\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?fit=300%2C115&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?fit=583%2C223&amp;ssl=1\" class=\"alignnone wp-image-21523 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?resize=583%2C223&#038;ssl=1\" alt=\"When multiple people are assigned to a single task\" width=\"583\" height=\"223\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?w=583&amp;ssl=1 583w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?resize=300%2C115&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?resize=150%2C57&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_09-1.png?resize=210%2C80&amp;ssl=1 210w\" sizes=\"auto, (max-width: 583px) 100vw, 583px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p>If you click \u201cProgresses by Resources\"(ribbon menu&gt; XLGantt tab &gt; Analysis group &gt; Progresses by Resources), you can check the result as follows.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21525\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_10-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?fit=801%2C522&amp;ssl=1\" data-orig-size=\"801,522\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_10\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?fit=300%2C196&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?fit=801%2C522&amp;ssl=1\" class=\"alignnone wp-image-21525 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?resize=801%2C522&#038;ssl=1\" alt=\"When multiple people are assigned to a single task\" width=\"801\" height=\"522\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?w=801&amp;ssl=1 801w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?resize=300%2C196&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?resize=150%2C98&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?resize=768%2C500&amp;ssl=1 768w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_10.png?resize=210%2C137&amp;ssl=1 210w\" sizes=\"auto, (max-width: 801px) 100vw, 801px\" \/><\/p>\n<p>&nbsp;<\/p>\n<h3>4) Application<\/h3>\n<p>If you enter \"Elsa [100%]\" in the \"Resources\" column, one person will be assigned full time (8 hours if a working condition is 8 hours a day), and if you enter \"Elsa [200%]\", Elsa will be assigned twice.<\/p>\n<p>By adopting this feature, the workload can be calculated as follows.<\/p>\n<p>If you don't know the names of the people assigned to the \u201cDesign database\u201d task, but 10 people are assigned, if you enter \u201cDesigner[10]\u201d, the workload is calculated as 10 designers are assigned to the task(designer[10] is the same as designer[1000%]).<\/p>\n<p><span style=\"color: #993300;\">Total workload = number of working days excluding nonworking days\u00a0 *\u00a0Number of entered persons (10 designers)<\/span><br \/>\n<span style=\"color: #993300;\">80 days = 8 days * 10 people<\/span><\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21527\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_11-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?fit=589%2C224&amp;ssl=1\" data-orig-size=\"589,224\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_11\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?fit=300%2C114&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?fit=589%2C224&amp;ssl=1\" class=\"alignnone wp-image-21527 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?resize=589%2C224&#038;ssl=1\" alt=\"designer[10] is the same as designer[1000%])\" width=\"589\" height=\"224\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?w=589&amp;ssl=1 589w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?resize=300%2C114&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?resize=150%2C57&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_11.png?resize=210%2C80&amp;ssl=1 210w\" sizes=\"auto, (max-width: 589px) 100vw, 589px\" \/><\/p>\n<p>&nbsp;<\/p>\n<h2>2. Calculated by weight<\/h2>\n<p>The \"Calculated by weight\" feature was provided before the upgrade to XLGantt version 4.0.<\/p>\n<p><em><span style=\"color: #ff0000;\">This feature is provided for compatibility with the previous version, and calculation is possible when only part of the person is allocated or when multiple people are allocated, but it is not recommended because there is a problem that the allocation ratio of a specific person cannot be specified.<\/span><\/em><\/p>\n<h3>1) When one person is assigned to one task<\/h3>\n<p>If nothing is entered in the \"Weight\" column or 1 is entered, the total workload is calculated as 8 days as one person is assigned.<\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21529\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_12-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?fit=628%2C223&amp;ssl=1\" data-orig-size=\"628,223\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_12\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?fit=300%2C107&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?fit=628%2C223&amp;ssl=1\" class=\"alignnone wp-image-21529 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?resize=628%2C223&#038;ssl=1\" alt=\"Calculated by weight\" width=\"628\" height=\"223\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?w=628&amp;ssl=1 628w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?resize=300%2C107&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?resize=150%2C53&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_12.png?resize=210%2C75&amp;ssl=1 210w\" sizes=\"auto, (max-width: 628px) 100vw, 628px\" \/><\/p>\n<p>&nbsp;<\/p>\n<h3>2) When a part of the resource is allocated to one task<\/h3>\n<p>If you enter \u201c0.5\u201d in the \"Weight\" column, only half will be calculated.<\/p>\n<p><span style=\"color: #993300;\">Total workload = number of working days excluding nonworking days\u00a0*\u00a0weight<\/span><br \/>\n<span style=\"color: #993300;\">4 days = 8 days * Weight 0.5<\/span><\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21531\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_13-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?fit=633%2C223&amp;ssl=1\" data-orig-size=\"633,223\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_13\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?fit=300%2C106&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?fit=633%2C223&amp;ssl=1\" class=\"alignnone wp-image-21531 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?resize=633%2C223&#038;ssl=1\" alt=\"Calculated by weight\" width=\"633\" height=\"223\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?w=633&amp;ssl=1 633w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?resize=300%2C106&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?resize=150%2C53&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_13.png?resize=210%2C74&amp;ssl=1 210w\" sizes=\"auto, (max-width: 633px) 100vw, 633px\" \/><\/p>\n<p>&nbsp;<\/p>\n<h3>3) When multiple people are assigned to a single task<\/h3>\n<p>If you enter 2 in the \"Weight\" column, it is calculated that two people are assigned.<\/p>\n<p><span style=\"color: #993300;\">Total workload = number of working days excluding nonworking days\u00a0*\u00a0weight<\/span><br \/>\n<span style=\"color: #993300;\">16 days = 8 days * Weight 2<\/span><\/p>\n<p><img data-recalc-dims=\"1\" loading=\"lazy\" decoding=\"async\" data-attachment-id=\"21533\" data-permalink=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/xlgantt_howto_14_en_14-2\/\" data-orig-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&amp;ssl=1\" data-orig-size=\"634,224\" data-comments-opened=\"1\" data-image-meta=\"{&quot;aperture&quot;:&quot;0&quot;,&quot;credit&quot;:&quot;&quot;,&quot;camera&quot;:&quot;&quot;,&quot;caption&quot;:&quot;&quot;,&quot;created_timestamp&quot;:&quot;0&quot;,&quot;copyright&quot;:&quot;&quot;,&quot;focal_length&quot;:&quot;0&quot;,&quot;iso&quot;:&quot;0&quot;,&quot;shutter_speed&quot;:&quot;0&quot;,&quot;title&quot;:&quot;&quot;,&quot;orientation&quot;:&quot;0&quot;}\" data-image-title=\"xlgantt_howto_14_en_14\" data-image-description=\"\" data-image-caption=\"\" data-medium-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=300%2C106&amp;ssl=1\" data-large-file=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&amp;ssl=1\" class=\"alignnone wp-image-21533 size-full\" src=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?resize=634%2C224&#038;ssl=1\" alt=\"Calculated by weight\" width=\"634\" height=\"224\" srcset=\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?w=634&amp;ssl=1 634w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?resize=300%2C106&amp;ssl=1 300w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?resize=150%2C53&amp;ssl=1 150w, https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?resize=210%2C74&amp;ssl=1 210w\" sizes=\"auto, (max-width: 634px) 100vw, 634px\" \/><\/p>\n<p>&nbsp;<\/p>\n<p>The workload is calculated even if the name of the resource is not entered in the \"Resources\" column.<\/p>\n<p>If 2 people's names are entered, the workload is calculated at a ratio of 100% (weight 2 \/ 2 people = 100%) for each person.<\/p>\n<p>If 3 people's names are entered with the weight of 2, the workload is calculated at a ratio of 66.7% (weight 2\/3 people = 66.7%) for each person, but there is a problem that the allocation ratio of a specific person cannot be adjusted.<\/p>\n<p><strong>If you select the \"Calculated by resource allocation ratio\" option, you can adjust the allocation ratio of a specific person.<\/strong><\/p>\n<p>&nbsp;<\/p>\n<p><strong>[ Using XLGantt(Excel Gantt) ]<\/strong><\/p>\n<ul>\n<li><a href=\"https:\/\/xlworks.net\/en\/xlgantt-project-scheduler\/\" target=\"_blank\" rel=\"noopener\">Excel WBS and Gantt Chart - XLGantt<\/a><\/li>\n<\/ul>\n<ul class=\"display-posts-listing\"><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-15-color-theme\/\">Excel Gantt Chart - How to #15 \u2013 Setting WBS Area and Color Theme<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\">Excel Gantt Chart - How to #14 \u2013 Workload calculation<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-13-server-data\/\">Excel Gantt Chart - How to #13 \u2013 Importing Server Data<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-12-integration-with-excel\/\">Excel Gantt Chart - How to #12 \u2013 Integration with Excel Features<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-11-calendar\/\">Excel Gantt Chart - How to #11 \u2013 Calendar<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-10-import-schedule\/\">Excel Gantt Chart - How to #10 \u2013 Importing Schedules<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-09-multilingual-support\/\">Excel Gantt Chart - How to #9 - Multilingual Support<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-08-add-tasks-to-outlook\/\">Excel Gantt Chart - How to #8 - Adding Tasks to Microsoft Outlook Calendar<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-07-deliverables\/\">Excel Gantt Chart - How to #7 \u2013 Deliverables<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-06-schedule-change-management\/\">Excel Gantt Chart - How to #6 \u2013 Managing Schedule Change<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-05-analysis-report\/\">Excel Gantt Chart - How to #5 \u2013 Analysis Report<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-04-project-progress\/\">Excel Gantt Chart - How to #4 \u2013 Keeping track the progress of the project<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-03-gantt-chart\/\">Excel Gantt Chart - How to #3 - Setting Gantt chart display styles<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-2-input-task-update-schedule\/\">Excel Gantt Chart - How to #2 - Enter tasks, Update schedule<\/a><\/li><li class=\"listing-item\"><a class=\"title\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-1-getting-started-with-xlgantt\/\">Excel Gantt Chart - How to #1 - Getting Started With XLGantt<\/a><\/li><\/ul>\n","protected":false},"excerpt":{"rendered":"<p>Let's take a look at how to calculate the workload when scheduling a project. As shown below, if the start date of the \u201cDesign database\u201d task is July 22 and the finish date is July 31, the working days(excluding nonworking days) are 8. &nbsp; \u203b [&hellip;]<\/p>\n","protected":false},"author":2,"featured_media":21533,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"site-sidebar-layout":"default","site-content-layout":"default","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","theme-transparent-header-meta":"default","adv-header-id-meta":"","stick-header-meta":"default","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"set","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"jetpack_post_was_ever_published":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","enabled":false},"version":2}},"categories":[984],"tags":[92,186,1023,1034],"class_list":["post-21506","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-xlgantt_howto","tag-xlgantt-en","tag-gantt-chart-en","tag-excel-gantt-en","tag-workload"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v25.1 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Excel Gantt Chart - How to #14 \u2013 Workload calculation - XLWorks<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Admin\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"5 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\"},\"author\":{\"name\":\"Admin\",\"@id\":\"https:\/\/xlworks.net\/en\/#\/schema\/person\/a1811d47aca1af1770b05a0a0938f33a\"},\"headline\":\"Excel Gantt Chart - How to #14 \u2013 Workload calculation\",\"datePublished\":\"2025-05-18T15:09:18+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\"},\"wordCount\":947,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/xlworks.net\/en\/#organization\"},\"image\":{\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1\",\"keywords\":[\"xlgantt\",\"gantt chart\",\"excel gantt\",\"Workload\"],\"articleSection\":[\"Using Excel Gantt\"],\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\",\"url\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\",\"name\":\"Excel Gantt Chart - How to #14 \u2013 Workload calculation - XLWorks\",\"isPartOf\":{\"@id\":\"https:\/\/xlworks.net\/en\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1\",\"datePublished\":\"2025-05-18T15:09:18+00:00\",\"breadcrumb\":{\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage\",\"url\":\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1\",\"contentUrl\":\"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1\",\"width\":634,\"height\":224,\"caption\":\"XLGantt(Excel Gantt) \u2013 Workload calculation\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Excel Program\",\"item\":\"https:\/\/xlworks.net\/en\/category\/excel_program\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Using Excel Gantt\",\"item\":\"https:\/\/xlworks.net\/en\/category\/excel_program\/xlgantt_howto\/\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Excel Gantt Chart - How to #14 \u2013 Workload calculation\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/xlworks.net\/en\/#website\",\"url\":\"https:\/\/xlworks.net\/en\/\",\"name\":\"\uc5d1\uc140\uc6cd\uc2a4\",\"description\":\"Excel Works!\",\"publisher\":{\"@id\":\"https:\/\/xlworks.net\/en\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/xlworks.net\/en\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/xlworks.net\/en\/#organization\",\"name\":\"XLWorks\",\"url\":\"https:\/\/xlworks.net\/en\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/xlworks.net\/en\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlworks_logo_new_w512.png\",\"contentUrl\":\"https:\/\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlworks_logo_new_w512.png\",\"width\":512,\"height\":512,\"caption\":\"XLWorks\"},\"image\":{\"@id\":\"https:\/\/xlworks.net\/en\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.instagram.com\/excelworks\/\",\"https:\/\/www.youtube.com\/c\/xlworks\"]},{\"@type\":\"Person\",\"@id\":\"https:\/\/xlworks.net\/en\/#\/schema\/person\/a1811d47aca1af1770b05a0a0938f33a\",\"name\":\"Admin\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/xlworks.net\/en\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/c51b70865d63eda5b2f50ebef685a6df4b9fac341c5132ce8541d9ba61101475?s=96&d=identicon&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/c51b70865d63eda5b2f50ebef685a6df4b9fac341c5132ce8541d9ba61101475?s=96&d=identicon&r=g\",\"caption\":\"Admin\"}}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Excel Gantt Chart - How to #14 \u2013 Workload calculation - XLWorks","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/","twitter_misc":{"Written by":"Admin","Est. reading time":"5 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#article","isPartOf":{"@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/"},"author":{"name":"Admin","@id":"https:\/\/xlworks.net\/en\/#\/schema\/person\/a1811d47aca1af1770b05a0a0938f33a"},"headline":"Excel Gantt Chart - How to #14 \u2013 Workload calculation","datePublished":"2025-05-18T15:09:18+00:00","mainEntityOfPage":{"@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/"},"wordCount":947,"commentCount":0,"publisher":{"@id":"https:\/\/xlworks.net\/en\/#organization"},"image":{"@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1","keywords":["xlgantt","gantt chart","excel gantt","Workload"],"articleSection":["Using Excel Gantt"],"inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/","url":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/","name":"Excel Gantt Chart - How to #14 \u2013 Workload calculation - XLWorks","isPartOf":{"@id":"https:\/\/xlworks.net\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage"},"image":{"@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1","datePublished":"2025-05-18T15:09:18+00:00","breadcrumb":{"@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#primaryimage","url":"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1","contentUrl":"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1","width":634,"height":224,"caption":"XLGantt(Excel Gantt) \u2013 Workload calculation"},{"@type":"BreadcrumbList","@id":"https:\/\/xlworks.net\/en\/xlgantt-howto-14-workloads\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Excel Program","item":"https:\/\/xlworks.net\/en\/category\/excel_program\/"},{"@type":"ListItem","position":2,"name":"Using Excel Gantt","item":"https:\/\/xlworks.net\/en\/category\/excel_program\/xlgantt_howto\/"},{"@type":"ListItem","position":3,"name":"Excel Gantt Chart - How to #14 \u2013 Workload calculation"}]},{"@type":"WebSite","@id":"https:\/\/xlworks.net\/en\/#website","url":"https:\/\/xlworks.net\/en\/","name":"\uc5d1\uc140\uc6cd\uc2a4","description":"Excel Works!","publisher":{"@id":"https:\/\/xlworks.net\/en\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/xlworks.net\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/xlworks.net\/en\/#organization","name":"XLWorks","url":"https:\/\/xlworks.net\/en\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/xlworks.net\/en\/#\/schema\/logo\/image\/","url":"https:\/\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlworks_logo_new_w512.png","contentUrl":"https:\/\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlworks_logo_new_w512.png","width":512,"height":512,"caption":"XLWorks"},"image":{"@id":"https:\/\/xlworks.net\/en\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.instagram.com\/excelworks\/","https:\/\/www.youtube.com\/c\/xlworks"]},{"@type":"Person","@id":"https:\/\/xlworks.net\/en\/#\/schema\/person\/a1811d47aca1af1770b05a0a0938f33a","name":"Admin","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/xlworks.net\/en\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/c51b70865d63eda5b2f50ebef685a6df4b9fac341c5132ce8541d9ba61101475?s=96&d=identicon&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/c51b70865d63eda5b2f50ebef685a6df4b9fac341c5132ce8541d9ba61101475?s=96&d=identicon&r=g","caption":"Admin"}}]}},"jetpack_publicize_connections":[],"jetpack_featured_media_url":"https:\/\/i0.wp.com\/xlworks.net\/wp-content\/uploads\/2025\/05\/xlgantt_howto_14_en_14.png?fit=634%2C224&ssl=1","jetpack_shortlink":"https:\/\/wp.me\/p7qvkj-5AS","jetpack_sharing_enabled":true,"_links":{"self":[{"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/posts\/21506","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/comments?post=21506"}],"version-history":[{"count":3,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/posts\/21506\/revisions"}],"predecessor-version":[{"id":21631,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/posts\/21506\/revisions\/21631"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/media\/21533"}],"wp:attachment":[{"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/media?parent=21506"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/categories?post=21506"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/xlworks.net\/en\/wp-json\/wp\/v2\/tags?post=21506"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}