Excel Gantt Chart - How to #5 – Analysis Report

한국어 (Korean)

XLGantt(Excel Gantt) provides you with analysis reports to help you keep track of your project.

When you click the buttons in the ribbon menu> XLGantt > Analysis Group, reports are created and several features are provided as follows.

XLGantt(Excel Gantt) ribbon menu

 

1. Progresses by Resources

It shows you the total workloads, planned workloads, progresses(%Work complete), etc.

  • When "by Resource Allocation Ratio" is selected in the "Workload Calculation" option – If you enter resources in the form of "John[50%], Elsa" in the resource field of the Schedule sheet, XLGantt calculates the workloads according to the percentage of the allocated resources.
  • When "by Weight" is selected in the "Workload Calculation" option – If you allocate multiple resources to one task, XLGantt calculates the workload assigned to one person by dividing the workloads by the number of people. For example, if you assign 3 people with a 9 Man/Day workload, XLGantt calculates that each person has 3 man/day allocated.

If a task has not been assigned to the person in charge, it is displayed as "(Resources unspecified)".

1) Progresses by Resources

Progresses by Resources

 

2) Subtotals

Click on the number of the subtotal level in the upper left corner to see subtotals.

Subtotals

 

2. Workloads (by weeks, months, Resources)

When you click "Workloads by Weeks", "Workloads by Months", "Workloads by Resources" in the ribbon menu, XLGantt displays the Workloads by charts.

Man-Month is one person's working time for a month

The working days are usually 21, but it can be changed to 20 days, 22 days, etc., and Man-Month is calculated and displayed based on the changed working days.

1) Workloads by Weeks

Workloads by weeks

 

2) Workloads by Months

Workloads by Months

 

3) Workloads by Resources

Workloads by Months

 

3. Project Progresses

Click "Progress by Weeks", "Progress by Months" on the ribbon to display the project progresses.

1) When not managing schedule changes

Only the "Planned workload progress" and "Earned value progress" are displayed.

When not managing schedule changes

 

2) When managing schedule changes

"Planned workload progress", "Earned value progress" and "Actual workload progress" are displayed.

When managing schedule changes

 

4. Export Workload data to the “Workload” sheet

If you click "Create Workload Data by Weeks", "Create Workload Data by Months" in the menu, Workload data is exported to the "Workload" sheet.
Using the "Workload" sheet data, you can perform analysis as desired by features such as Excel pivot.

Export Workload data to the “Workload” sheet

 

 

[ Using XLGantt(Excel Gantt) ]

한국어 (Korean)

엑셀웍스 책 출간 안내

그동안 엑셀웍스에 올린 '엑셀 강좌', '함수 사용법', 여러 '실무 예제'에서 핵심만 뽑아 '된다! 엑셀 수식 & 함수' 책으로 출간하였습니다.

 자세히 보기

온라인 구매처: 예스24   교보문고   알라딘 

Leave a Reply

Scroll to Top