Excel Gantt Chart - How to #6 – Managing Schedule Change

한국어 (Korean)

In Excel Gantt, you can use actual start and finish dates. So You can identify the schedule is delayed or ahead by entering the actual start and finish dates.

1. Schedule change management setting

Click the "Options" button on the ribbon menu > XLGantt tab to choose schedule option.

Schedule change management setting

 

If you choose "Managing Schedule Changes",  the following fields are displayed: Actual Start Date, Actual Finish Date, and Actual Total Work.

Schedule change

 

2. How to enter the changed schedule

There are three ways to enter the changed schedule.

1) When the task is completed and you enter the actual start date and actual finish date.

  • If you enter the actual start date and the actual finish date directly, the %Work Complete is automatically entered as 100%.
  • If the planned schedule differs from the actual schedule, the background color of the date is displayed in yellow and the Gantt chart displays the actual schedule in blue lines.

How to enter the changed schedule

2) If a task is completed as planned

If a task is completed on the same schedule as the planned schedule, you can enter 100% of the %Work Complete only. If you do not enter the actual start date and actual finish date, they will be filled with the same date as the planned start date and finish date.

 

3) If a task is not completed yet

If a task is not completed, enter only the actual start date and the %Work complete. If you enter the actual finish date, the task is considered completed, so you only need to enter the actual start date.

 

 

[ Using XLGantt(Excel Gantt) ]

한국어 (Korean)

엑셀웍스 책 출간 안내

그동안 엑셀웍스에 올린 '엑셀 강좌', '함수 사용법', 여러 '실무 예제'에서 핵심만 뽑아 '된다! 엑셀 수식 & 함수' 책으로 출간하였습니다.

 자세히 보기

온라인 구매처: 예스24   교보문고   알라딘 

Leave a Reply

Scroll to Top